14) Whenever an activity has zero total float, then
Answer is:
free float and independent float both must be zero
Related Structural Engineering II MCQ with Answers
Answer is:
its latest start time and earliest start time
Answer is:
Critical activity is the one for which free float is zero.
Answer is: