31) The normal time required for the completion of project in the above problem is
Answer is:
14 days
Related Structural Engineering II MCQ with Answers
Answer is:
project duration time
Answer is:
all of these
Explanation:
Updating may result in
* change of critical path
* decrease of project completion time
* increase of project completion time
Answer is: