23) The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
Answer is:
independent float
Related Structural Engineering II MCQ with Answers
Answer is:
normal time
Answer is:
between normal time and crash time
Answer is:
minimum
Explanation:
The direct cost of a project with respect to normal time is minimum.