21) A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and sometimes as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be
Answer is:
21 minutes
Related Structural Engineering II MCQ with Answers
Answer is:
independent float
Answer is:
normal time
Answer is: